6
Initial operation
Logano plus SB615 Gas - We reserve the right to make any changes due to technical modifications.
34
6
Initial operation
This chapter describes how to start up the heating
system.
B
Perform start up according to the user manuals for the
boiler, burner, low water indicator and electronic
heating circuit control.
B
When handing over the system, show the operator how
it functions and how to operate it, and hand over the
technical documentation to them. Complete the
commissioning report.
B
Draw the operator's attention to the maintenance
requirements and recommend arranging a
maintenance contract.
6.1
Flushing the heating system
Flush the heating system prior to commissioning to
prevent contamination that could e.g. block and damage
the circulation pump.
CAUTION:
System damage due to heavy
dust deposits!
B
Do not operate the boiler where heavy
dust contamination persists, e.g. through
building work inside the boiler room.
DANGER:
Risk to health from drinking water
contamination!
B
Always observe the regulations and
standards applicable in your country for
the prevention of contamination of
drinking water (e.g. by water from heating
systems).
B
Observe EN 1717.
CAUTION:
Boiler damage from corrosion
and sludge!
B
It is essential to flush the entire heating
system before filling with heating water.
B
Check the quality of the fill and top-up
water, so as to avoid scaling and
corrosion. (Note the “Water treatment...”
operator's log.)
If a heating system contains several heating
circuits, these must be flushed one after the
other.