5
Installation of the boiler
Logano plus SB615 Gas - We reserve the right to make any changes due to technical modifications.
22
5.13
Fitting the back plate
For boiler sizes 145 kW to 310 kW, the rear wall is in two
parts (
Æ
Fig. 14), for boiler sizes 400 kW to 640 kW only
one part (
Æ
Fig. 15).
Boiler sizes 145 kW to 310 kW
B
Secure the lower boiler cover [1] with 5 self-tapping
screws [2] to the side panels.
B
Insert the upper rear panel section [4] with the Z-fold
behind the lower rear panel section, and secure onto
the side panels with four self-tapping screws [3].
B
Make sure that the two upper self-tapping screws also
pass through the connection plates.
B
Secure one or two cable clips [5] or a cable duct on the
fold on the upper rear panel section.
Fig. 14 Screwing the 2-part real panel in place (boiler
rating 145 to 310 kW).
1
Lower rear panel
2
5 self-tapping screws
3
4 self-tapping screws
4
Upper rear panel
5
Cable clamp/cable channel
Boiler sizes 400 kW to 640 kW
B
Secure the boiler cover [1]with 4 self-tapping screws
on the right and left-hand side to the side panels.
B
Make sure that the two upper self-tapping screws also
pass through the connection plates.
B
Secure one or two cable clips [2] or a cable duct on the
fold on the rear panel section.
Fig. 15 Screwing rear panel in place (boiler rating 400
to 600 kW)
1
Back panel
2
Cable clamp/cable channel