Installation of the boiler
Logano plus SB615 Gas - We reserve the right to make any changes due to technical modifications.
14
5
Installation of the boiler
This chapter explains how to correctly install the boiler.
5.1
Checking delivery for completeness
B
Upon delivery, check all packaging for damage.
B
Check the delivered package(s) for completeness
(
Æ
Chapter 2.4).
5.2
Disposing of packaging
B
Dispose of packaging in an environmentally
responsible manner.
5.3
Minimum clearances / product
dimensions
5.4
Changing the hinging of the burner
door
The burner door can be moved from the right-hand side
(factory-set) to the left-hand side.
B
Push the hinge bolts out of the hinges from underneath
[1].
B
Refit the washer [2] and the two hinge pins to the
adjacent hinges. Make sure that the washer is
re-installed.
Fig. 4
Reversing the door hinges
1
Hinge pin
2
Washer
CAUTION:
System damage due to open
combustion chamber!
The combustion chamber must remain
sealed by the burner door so that the
stainless steel combustion chamber is not
damaged by any welding or grinding work.
B
Ensure when fitting the front thermal
insulation pad that the combustion
chamber remains sealed by the burner
door.
Observe the recommended minimum wall
clearances when positioning (
Æ
Tab. 3,
page 11).
DANGER:
Risk of injury from unsupported
door!
B
Change the door hinging only when the
door is closed and bolted.