16.2 Inspection report
z
Please indicate the inspection activities that you have
carried out and enter the values measured.
Inspection activities
page Date: ______
Date: ______
Date: ______
1. Test the general condition of the heating system
2. Carry out a visual inspection and test the functions of the
heating system
3. Test all gas and water conduits and fittings for:
– their tightness during operation
– visible corrosion
– signs of aging
– fill the condensate trap
48
47
32
4. Check the burner, the heat exchanger and the condensate trap for
pollution. First shut down the heating system
49
5. Check the burner and the ignition and ionization electrodes.
First shut down the heating system
49
6. Measure the ionization current
37
_______ µA
_______ µA
_______ µA
7. Measure the gas connection pressure (flow pressure)
33
_______ psi
_______ psi
_______ psi
8. Check the gas/air ratio
34
_____ inch W.C. _____ inch W.C. _____ inch W.C.
9. Carry out a gas tightness test in operating conditions
48
10. Measure the carbon monoxide content (CO)
48
_______ ppm
_______ ppm
_______ ppm
11. Check the water pressure of the heating system
– Inlet pressure of expansion tank (also see the
Installation Instructions for the expansion tank)
– Filling pressure
30
30
_______
_______ psi
_______ psi
12. Check the operation and safety of the air intake and flue pipe
32
13. Check that the thermostat is set in line with the needs
(see documents with thermostat)
39
14. Final check of inspection activities, note down the measurement
and test results
15. Confirm proper inspection
Company
stamp/signature
Company
stamp/signature
Company
stamp/signature