16 Reports
16.1 Start-up report
Put your signature and the date at the bottom of the start-up
report.
Start-up activities
Page
Measured values
Remarks
1. Fill the heating system and check that all connections are tight
– Inlet pressure of expansion tank (observe the Installation Instructions
for the expansion tank)
– Pressurize the system
– Fill the condensate trap
30
30
30
30
__________ psi
__________ psi
2. Carry out a gas tightness test
30
3. Note down the gas characteristics:
Wobbe index
Operating heat value
30
__________ kWh/m³
__________ kWh/m³
4. Convert the boiler to another type of gas supply (only if allowed)
52
5. Vent the gas supply conduit
32
6. Check the combustion air/flue gas connection
32
7. Measure the gas connection pressure (flow pressure)
33
________ inch W.C.
8. Check and adjust the gas/air ratio
34
________ inch W.C.
9. Measure the carbon monoxide content (CO)
36
__________ ppm
10. Check and if necessary adjust the carbon monoxide content (CO
2
)
__________ %
11. Measuring the ionization current
37
__________ µA
12. Make the necessary settings on the thermostat
39
13. Carry out function testing
36
14. Fitting the casing
38
15. Inform the owner; hand over the technical documents
38