Highway Class Paver/Finishers
Drive Train
A-70
INSTALLATION
Step 1:
Install wheel spindle.
a. Lift spindle (7) into position using a lifting device.
b. Install four bolts that secure spindle to machine
frame. Do not tighten these bolts until drive
chain is tensioned.
6
5
7
8
0760-87A
Step 2:
Install chain tensioner.
a. Put chain tensioner (6) in place.
b. Secure chain tensioner with two bolts (5) on
spindle.
Step 3:
Grease bearings. Tap bearings into place.
Step 4:
Install wheel hub.
a. Slide hub on spindle.
b. Install retaining washer (4).
c. Install inner lock nut (3).
d. Tighten nut and adjust rolling torque to 40-80
lb-in (54-108 N•m).
e. Install lock washer (2) and bend one tab on
inner nut notch.
f. Install outer lock nut (1) and hand tighten, bend
one tab of lock washer (2) on outer nut notch. If
necessary, back nut off slightly to align tab with
notch.
3
1
2
4
BK-164
Step 5:
Install tire.
a. Place tire on hub.
b. Install lug nuts to secure tire. Torque lug nuts to
320 lb-ft (434 N•m) dry torque, 240 lb-ft (325
N•m) wet torque.
0760-79
IMPORTANT
When assembling drive chain, make sure cotter
pin is on chain side that faces machine frame.
Step 6:
Install drive chain.
a. Place chain over drive tire sprocket and the axle
sprocket.
b. Install link pins.
c. Install cotter pins (9) to master link. This will
secure chain.
d. Adjust chain tension as explained in DRIVE
CHAIN AND TIGHTENER ASSEMBLY.
e. Install chain guard.
9
1144-82B