StEP 5
(Installing The POWERSIDE Column)
1. Before proceeding, double the check measurements
and make certain that the bases of each Column are
aligned with the chalk line.
2. Using the base plate on the POWERSIDE column as a
guide, drill each anchor hole in the concrete (approximately
4” deep for 10K models and 6” deep for 12K and15K;
8” for 18K models) using a rotary hammer drill and 3/4”
concrete drill-bit. To assure full holding power, do not ream
the hole or allow the drill to wobble. (See Fig. 5.1)
3. After drilling, remove dust thoroughly from each hole
making certain that the Column remains aligned with the
chalk line.
4. Assemble the washers and nuts on the anchors
then tap into each hole with a hammer until the washer
rests against the Base Plate. Be sure that if shimming is
required that enough threads are left exposed.
(See Fig. 5.2)
5. If shimming is required, insert the shims as necessary
under the Base Plate so that when the anchor bolts are
tightened, the Columns will be plumb. (See Fig. 5.3)
6. If installing the Optional Foot Guards, place foot guards
on left and right side as shown. (See Fig 5.4)
7. With the Foot Guards, shims and anchor bolts in place,
tighten by securing the nut to the base then turning 3-5 full
turns clockwise.
Do Not
use an impact wrench for this
procedure. (See Fig. 5.5)
Fig 5.1
Fig 5.2
Fig 5.3
NotE:
To ease installation of the Top Trough, it helps to keep
the anchor bolts loose on one of the Columns until the
Top Trough is mounted.
Fig 5.4
Fig 5.5
IMPoRtANt NotE:
BendPak lifts are supplied with installation
instructions and concrete fasteners meeting the
criteria as prescribed by the American National
Standard "Automotive Lifts - Safety Requirements for
Construction, testing, and Validation" ANSI/ALI
ALCtV-2006. Lift buyers are responsible for any
special regional structural and/or seismic anchoring
requirements specified by any other agencies and/or
codes such as the Uniform Building Code (UBC)
and/or International Building Code (IBC).
Содержание XpR-10AC-168
Страница 25: ...25 25 ...
Страница 28: ...28 ...
Страница 32: ...32 32 OPTIONAL EQUIPMENT INSTALLATION ...
Страница 42: ...42 42 ...
Страница 43: ...43 43 ...
Страница 52: ...52 52 ...
Страница 74: ...74 ...
Страница 75: ...75 ...