INSTALLATION
SETUP AND PHYSICAL INSTALLATION
3 - 6
I-E96-202B
®
To execute special operations:
1. Set pole 1 of dipswitch SW4 to the open (off) position.
2. Set poles 2 through 8 for the desired operation in accor-
dance with Table
3. Insert the module into its assigned slot in the module
mounting unit.
4. When the special operation is complete, the module status
LED turns red and LEDs 1 through 6 illuminate.
5. Remove the module.
6. Repeat Steps 2 through 5 for any other desired special
operation.
NOTE: Special operation 2 should be done as the first step of the
installation process. When installing the MFP module in an
INFI-NET system, do special operation 4 next. If time stamping is
desired, do special operation 6 next. To reverse the INFI-NET proto-
col or time stamping, do special operation 2 again.
7. Set pole 1 to the closed (on) position.
8. Set poles 2 through 8 in accordance with Table
9. Insert the module into its assigned slot. The module will
enter configure mode.
Jumpers J1 through J5
There are five jumpers on the MFP circuit board. See Figure
for jumper locations. Jumpers J1 through J4 direct signals
to the termination unit or module. These jumpers are factory
set with pin one and pin two connected together.
Do not
change these jumper settings.
Jumper J5 disconnects -30 VDC, supplied in early Network 90
systems, from the MFP module. It also allows the module bus
to be used. In later Network 90 and INFI 90 systems, this
jumper disconnects Controlway Channel B limiting communi-
cation to the module bus. This jumper is factory set with pin
one and pin two connected. This setting allows the module to
function in early Network 90 systems (-30 VDC supplied to
modules) or limits communication to the module bus in later
Network 90 and INFI 90 systems. Connect pin two and pin