8 .1 .2 Starting-up
•
Switching On
(see "Commissioning" chapter
OK
Non conforming
Engage the main circuit breaker of the installation (outdoor unit power supply)
2 hours before carrying out the tests => Pre-heat the compressor.
Engage the ON/OFF switch => Initialisation within a few seconds.
Operation of the heating circulation pump
The outdoor unit starts after 4 min.
Set the hour, Date and timer Programmes CC, SHW, if different from the default values.
Configure the hydraulic circuit (parameter 5700).
Set the heating curve (720 and 1020).
Adjust the max. initial ref. value (741 and 1041)
•
Outdoor unit checks
OK
Non conforming
Value
Operation of fan(s), compressor
Current measurement.
After a few minutes, measurement of air temp. delta.
Check the pressure / temperature of condensation and evaporation.
•
Hydraulic unit checks
OK
Non conforming
Value
After 15 mins of operation.
Primary water temp. delta.
Priority to SHW (switch of directional valve).
Heating in operation, boiler measurement...
•
Room control
(see chapter "Configuration de the Ambient probe"
§
OK
Non conforming
Set parameters, handling, checks.
Set the timer programme of the heating periods (500 to 516 / 520 to 536)
Set the reference values of the heating circuits if different from the default values (710 - 714 ; 1010-
1014).
Set the reference values SHW (1610-1612), if different from the default values .
Setpoint display.
Explanations on use.
The heat pump is ready for operation !