Installation Verification
Service and Maintenance Procedures
129359-452, Volume 1
2.2
Filling/Starting Optional Electric Steam Generator Boiler
(If Equipped) (See Figure 2-2)
1. Verify that the steam-to-jacket valve is closed.
NOTE: Water to sterilizer must also be turned on.
2. Open the drain valve on the side of the unit.
3. Open the water-level sight glass valves and water supply valve if they are
closed.
NOTE:Water supply is three position valve. Rotate quickly 180° counterclock-
wise.
4. Position the main electric power disconnect switch to ON. (The main
disconnect switch is not part of the generator.)
5. Position the sterilizer power switch to the ON position. Water will flow into the
generator and out of the drain valve, flushing out the boiler.
6. Allow the unit to flush for at least 3 minutes; then close the drain valve. The
generator will fill to the proper working level and then start to heat.
7. Open the steam-to-jacket valve slowly when the generator has reached
proper operating pressure (within 10 minutes after flushing).
Figure 2-2. Optional Steam Generator