ATEX (Zone 1 and 21 purging system
installation)
GasEye Cross Duct
Operating instructions, 05/2021
201
ATEX (Zone 1 and 21 purging system installation)
The GasEye Cross Duct (Ex1 version only) can be operated in Zone 1 and 21 and
provide the optical radiation to Zone 0 and 20 per mark II (1)/2G [Ex pxb op is T6 Ga]
IIC Gb and II (1)/2D [Ex pxb op is T6 Da] IIIC Db.
Any other ways of using the GasEye Cross Duct are forbidden.
Basic requirements and safe use
The manufacturer will not be liable for damage resulting from incorrect installation,
failure to maintain the device in a suitably functional condition, or use of the device
other than for its intended purpose.
Installation should be carried out by qualified personnel having the necessary
authorization to install electrical and pressure measuring devices. The installer is
responsible for performing the installation in accordance with these instructions and
with the electromagnetic compatibility and safety regulations and standards
applicable to the type of installation.
The device should be configured appropriately for the purpose for which it is to be
used. Incorrect configuration may cause erroneous functioning, leading to damage to
the device or an accident.
Installation of device should be performed with particular care, in accordance with the
regulations and standards applicable to that type of installation.
The general rules for connecting and using pressurized enclosure should conform to
the rules and standards for equipment with Ex p as specified in:
- IEC 60079-14: Explosive atmospheres. Electrical installations design,
selection and erection.
- IEC 60079-17: Explosive atmospheres. Electrical installations inspection and
maintenance.
The GasEye is designed and manufactured in accordance with following standards:
- EN IEC 60079-0:2018;
- EN 60079-2:2014;
- EN 60079-26:2015
- EN 60079-28:2015
Содержание GasEye
Страница 1: ......
Страница 2: ...Introduction 2 GasEye Cross Duct SG and MG Operating instructions 05 2021...
Страница 4: ...Introduction 4 GasEye Cross Duct SG and MG Operating instructions 05 2021...
Страница 8: ...Introduction 8 GasEye Cross Duct SG and MG Operating instructions 05 2021...
Страница 21: ...Technical data GasEye Cross Duct Operating instructions 05 2021 21 Figure 8 Calibration certificate...
Страница 188: ...WebServer application 188 GasEye Cross Duct SG and MG Operating instructions 05 2021 Figure 180 Alarm parameters window...