Commissioning
Commissioning
Airedale do not offer any commissioning services for the Artus. Mechanical commissioning,
including water side balancing, must be completed by others before Airedale or other third party
Siemens Solution Partners configure the Artus(s) for master/slave operation, room operator units,
BMS integration and so forth.
CAUTION
Step 1
Remove insulation
around the
Pressure Independent Control Valve
to access binder points
and
valve preset dial
.
Step 2
Using the binder points
, measure the
differential pressure across the valve
.
If the measured differential pressure is
higher than the start-up pressure (>35kPa),
the valve is keeping the flow stable at the
preset value.
Step 3
Ensure velcro lined insulation
is reattached to the unit after
measurements have been taken.
Item
Description
Lined Insulation
Pressure Independent Control Valve (PICV)
Binder Insertion Points
Pressure Gauge (supplied by others)
PICV Valve Preset Dial
Pressure Independent Control Valve (PICV)
The valve is factory set to position 9. Please refer to the table overleaf for alternative settings.
Electrical power is needed at the unit to drive the valve gear during waterside commissioning.
Electrical installation and commissioning must be fully completed before the waterside installation
and commissioning can take place.
CAUTION