PROBOIL.2X user & installation guide v1e-2
34
8.
Check that the red 3/8” x 8mm boiler outlet connector (
J
) has
preinserted internally the 3/8” rubber seal (I),
an additional
seal is supplied, ensure to use only 1 x 3/8” rubber seal in this
connection.
9.
Screw the red 3/8” x 8mm boiler outlet connector (
J
) hand tight
(
do not use a spanner or overtighten
) on to the boiler 3/8”
male outlet (
C
).
10.
Plug the power cable (
D
) securely into the socket on the left-
hand side of the boiler (A).
11.
Hook the boiler keyhole slots onto its wall fixing screws (
M
) and check it is secure.
12.
Take the ¼” blue flexible pipe (
E
) that caries the cold filtered
water output from the filter and rough out the minimum
amount of pipe needed to connect to the ¼” x ¼” pushfit
connector (
F
) found on the boiler inlet.
Mark the desired minimum pipe length with a permanent pen.
We recommend cutting the ¼” blue flexible pipe (
E
) at
least 200mm longer than the required minimum pipe length to
allow the boiler to be serviced more easily by your customer,
otherwise remove unnecessary/unneeded pipe length to keep
the installation tidy.
Cut the ¼” blue flexible pipe (
E
) to length cleanly and squarely
using a snip tool, sharp craft blade or similar.
13.
Push the ¼” blue flexible pipe (
E
) fully and firmly into the ¼” x
¼” pushfit connector (
F
)
14.
Firmly and fully push the silicone outlet tube (
K
) over the 8mm
barbed stem x 3/8” male tap connector (
L
).
15.
Screw the 8mm barbed stem x 3/8” male tap connector (
L
) into
the 3/8” female flexible 110°C hose tap connector (
Q
),
you
must ensure to use 3/8” the fibre seal (Q) (supplied separately
with the tap) is in this connection.
⚠
WARNING
:
You must not directly connect the tap hose
(Q) directly to the boiler output (C). You must always use
output adaptor (J) and silicone hose (K) to connect the tap.