Electrical installation 45
4. Tighten the two tightening screws so that the EMI conductive cushions press tightly
round the bare shield.
5. Secure the cables mechanically at the lead-through strain relief.
6. Keep the shields continuous as close to the connection terminals as possible.
Note:
If the outer surface of the shield is non-conductive:
•
Cut the shield at the midpoint of the bare part. Be careful not to cut the conductors or
the grounding wire (if present).
•
Turn the shield inside out to expose its conductive surface.
•
Cover the turned shield and the stripped cable with copper foil to keep the shielding
continuous.
Note for top entry of cables:
When each cable has its own rubber grommet, sufficient IP
and EMC protection can be achieved. However, if very many control cables come to one
cabinet, plan the installation beforehand as follows:
1. Make a list of the cables coming to the cabinet.
2. Sort the cables going to the left into one group and the cables going to the right into
another group to avoid unnecessary crossing of cables inside the cabinet.
3. Sort the cables in each group according to size.
4. Group the cables for each grommet as follows ensuring that each cable has a proper
contact to the cushions on both sides.
Cable diameter in mm
Max. number of cables per grommet
< 13
4
< 17
3
< 25
2
> 25
1
a
EMI conductive cushion
b
Strain relief
c
Grommet
d
Lead-through plate
a
b
c
d
A
Stripped cable
B
Conductive surface of the shield exposed
C
Stripped part covered with copper foil
1
Cable shield
2
Copper foil
3
Shielded twisted pair
4
Grounding wire
1
A
B
C
2
2
3
4
Содержание ACS880-1607
Страница 1: ...ABB industrial drives Hardware manual ACS880 1607 DC DC converter units ...
Страница 4: ......
Страница 12: ...12 Introduction to the manual ...
Страница 34: ...34 Mechanical installation ...
Страница 40: ...40 Guidelines for planning electrical installation ...
Страница 52: ...52 Electrical installation ...
Страница 68: ...68 Start up ...
Страница 80: ...80 Maintenance 7 3 4 5 6 ...
Страница 82: ...82 Maintenance 3 4 5 6 7 8 9 9 ...
Страница 85: ...Maintenance 85 12 Install and tighten the two screws 10 11 12 ...
Страница 92: ...92 Maintenance 3 6 4 5 4 7a 7b 7b ...
Страница 93: ...Maintenance 93 9 8 8 10 11 ...
Страница 96: ...96 Maintenance 4 8 6 7 5 3 ...
Страница 97: ...Maintenance 97 9 ...
Страница 118: ...118 Dimensions Dimension drawings Frame 1 R8i bottom cable entry ...
Страница 119: ...Dimensions 119 Frame 1 R8i top cable entry ...
Страница 120: ...120 Dimensions Location and size of input terminals Frame 1 R8i bottom cable entry Frame 1 R8i top cable entry ...
Страница 122: ...www abb com drives www abb com drivespartners 3AXD50000023644 Rev B EN 2017 01 30 Contact us ...