Start-up with low voltage stator 41
3
Start-up with low voltage stator
What this chapter contains
This chapter describes the basic start-up procedure of the wind turbine converter equipped
with doubly-fed induction generator control program.
Note:
Grid-side converters are delivered with one of the following grid voltage
measurement methods:
•
The grid-side converter receives the voltage measurement data from the rotor-side
converter. (The rotor-side converter is only fitted with an NUIM board.)
•
The grid-side converter is fitted with a dedicated measurement board, NAMU / BAMU.
Each method requires a different grid-side converter control program version. The first
method requires version IXXR7260 with Adaptive program version IZXX0169.AP (or later
versions) while the second requires version IWXR7300 with Adaptive program version
00595631_C.AP (or later versions).
The grid-side converter parameter settings in the start-up procedure below differ
depending on which grid voltage measurement method is used.
ISU
INU
G
Stator breaker
Содержание ACS800-67
Страница 1: ...ABB wind turbine converters System description and start up guide ACS800 67 wind turbine converters ...
Страница 4: ......
Страница 76: ...76 Start up with medium voltage stator ...
Страница 99: ...Practical examples 99 1 4 4 3 2 5 6 7 ...
Страница 106: ...106 Practical examples Counterclockwise rotation at drive end D end Power cabinet Encoder ...
Страница 118: ...118 Tracing the source of warnings limits and faults ...
Страница 120: ...Contact us www abb com windconverters 3AUA0000095094 Rev B EN 2017 12 31 ...