40 System description
Phasing checks executed at start-up
During the encoder calibration and voltage synchronization, the software ensures that the
grid, encoder, stator and rotor phasings are correct. The U-phase (and V- and W-phase) of
the grid is connect to the U-phase of the stator via main circuit breaker.
The following checks are automatically executed at start-up in the order in which they are
listed:
Grid phasing
Grid flux is a measured quantity. The angle of the flux is calculated. The angle is derivated
and filtered. As a result, angular speed of the grid flux is received. If the speed is negative,
the grid phasing is incorrect.
Encoder phasing
The generator actual speed is received from the encoder speed feedback. If the direction
is negative, the encoder phasing is wrong.
Note:
This check is executed only if RUN command has been issued.
Stator phasing
During normal operation, the grid flux and the stator flux rotate clockwise at the grid
frequency. If the sum of the rotor flux speed and slip does not rotate at the frequency of the
stator flux, the stator phasing is incorrect.
Note:
The rotation speed of the rotor flux is independent of whether the rotor phasing is
correct or not.
Rotor phasing
The dot product between the two flux vectors is approxi1 when the rotor phasing
is correct and approximately -1 when the rotor phasing is incorrect.
Stator
Grid
Main circuit breaker
U
V W
U
W
V
NUIM-6x
Commissioning phasing requirement
Содержание ACS800-67
Страница 1: ...ABB wind turbine converters System description and start up guide ACS800 67 wind turbine converters ...
Страница 4: ......
Страница 76: ...76 Start up with medium voltage stator ...
Страница 99: ...Practical examples 99 1 4 4 3 2 5 6 7 ...
Страница 106: ...106 Practical examples Counterclockwise rotation at drive end D end Power cabinet Encoder ...
Страница 118: ...118 Tracing the source of warnings limits and faults ...
Страница 120: ...Contact us www abb com windconverters 3AUA0000095094 Rev B EN 2017 12 31 ...