Chapter 3: Configuration and commissioning
ZP1-F Series Installation Manual
71
Functional tests
Create a short and open circuit in the zone to test fault reporting for each.
Activate a manual call point to test manual alarm reporting. The control panel
should override any configured delays and activate alarm notification devices and
fire routing (where applicable) immediately.
Activate a detector to test automatic alarm reporting. The control panel should
initiate any configured delays and activate alarm notification devices and fire
routing (where applicable) once the delay time has elapsed.
Using a multimeter, verify that the fault relay is activated when a fault is reported
and that the alarm relay is activated when an alarm is reported.
Response times
Response times for standard events are as follows.
Table 29: Response times for standard events
Event
Response time
Alarm
Less than 3 seconds
Zone fault
Less than 30 seconds
Sounder fault
Less than 30 seconds
Fire routing fault
Less than 30 seconds
Expansion board fault
Less than 100 seconds
Network fault
Less than 100 seconds
Earth fault
Less than 100 seconds
Battery charger fault
Less than 100 seconds
No batteries found fault
Less than 3 minutes
Mains fault
Less than 3 minutes
Out of service fault
Less than 100 seconds
Fuse/protection fault
Less than 3 minutes
System fault
Less than 100 seconds
Battery high resistance fault Less than 4 hours
Summary of Contents for ZP1-F2
Page 1: ...ZP1 F Series Installation Manual P N 501 415603 1 60 ISS 12DEC22...
Page 78: ...Chapter 3 Configuration and commissioning 72 ZP1 F Series Installation Manual...
Page 82: ...Chapter 4 Maintenance 76 ZP1 F Series Installation Manual...
Page 94: ...Chapter 5 Technical specifications 88 ZP1 F Series Installation Manual...
Page 106: ...Appendix A Configuration presets 100 ZP1 F Series Installation Manual...
Page 110: ...Appendix B Regulatory information 104 ZP1 F Series Installation Manual...
Page 113: ......