Installation
___________________________________________________________________________________
___________________________________________________________________________________
- 243 -
1.6) Lay the indoor pipeline
Note: Collocate the air-outlet reasonably to prevent airflow short-circuit. Check the static
pressure whether in the allowable range. The air filters should be easy to unpick and wash. Do
pressure test on pipeline.
1.7) Heat-insulation
Procedure:
Note: For welding part, flare part and branch pip, heat-insulation work must be done after
finished the pressure test.
1.8) Install outdoor unit
Procedure:
Note: 1. Gutter must be set around the foundation to drain the condensation water.
2. When installing outdoor units at the housetop, please check the strength of the
housetop and pay attention not to destroy the waterproof of the housetop.
1.9) Recharge refrigerant
Procedure:
Note: Please must use the correct formula that we supplied and the calculation results must be
correct.
1.10) Main points of test running and debugging
Please check the following issues before turning on the power:
1. Vacuum dry: make sure the vacuum degree accord with our requirement about 10-5.
Summary of Contents for R-410A
Page 103: ...Wall mount 102 Part 4 2 Wall Mounted...
Page 113: ...Wall mount 112 4 Dimensions 4 1 YDS 22 36EC 4 2 YDS 45 56EC...
Page 115: ...Wall mount 114 5 Piping Diagrams 5 1 YDS 22 56EC 5 2 YDS 22 56HC...
Page 116: ...Wall mount 115 6 Wiring diagrams 6 1 YDS 22 36EC 6 2 YDS 45 56EC...
Page 117: ...Wall mount 116 6 3 YDS 22 56HC...
Page 118: ...Wall mount 117 7 Sound level 7 1 Test condition 7 2 Noise spectrums YDS 22 36EC HC...
Page 119: ...Wall mount 118 YDS 45 56EC HC...
Page 120: ...Wall mount 119 8 Velocity temperature distribution Discharge angle 70...