You have finished squaring your
eave walls.
Leave your temporary brace
in place until you finish
attaching your roof panels.
45
TP Brace
EAVE WALL SQUARING
TP
144"
(365,8 cm)
61"
(154,9 cm)
HINT:
FINISH
PARTS REQUIRED:
3" (7,6 cm)
x8
x3
2 x 4 x 96" (5,1 x 10,2 x 243,8 cm)
TP
Temporary Brace
BEGIN
Assemble two
TP
’s with edges flush to 144” length using (3) 3” screws as shown
(Fig. A)
.
At the middle stud
(Fig. C)
install brace flush under top plate at each end using (1) 3” screw
(Fig. A).
Measure from end of brace (inside wall panel) 61” (154,9 cm) and mark a vertical line on brace
(Fig. A
and B)
.
Locate a
TP
in approximately the position shown in
Fig. A
and attach at lower end using (1) 3” screw.
With assistance, push or pull the wall until
TP
is flush to the mark and top of brace
(Fig. A, B and C)
.
Secure
TP
onto brace
(Fig. B)
using (2) 3” screws.
1
2
3
I
Flush TP Brace up under top plate.
Secure using 3" screws
(3) 3" (7,6 cm)
Screws
Fig. C
Fig. B
Fig. A
Flush
Flush
TOP
PLATE
MIDDLE
STUD
Mark
Flush
Flush