RT70 Operator’s Manual
Maintenance - 189
Trencher Procedures
Install Chain
1. Lay chain on ground with teeth down and pointed toward unit.
2. Fasten and adjust seat belt.
3. Start engine.
4. Release parking brake.
5. Back unit up until chain extends past headshaft about 1’ (305mm).
6. Stop machine movement.
7. Lower backfill blade, if equipped, to ground.
8. Lower boom to horizontal position.
9. Set parking brake.
10. Shut off machine.
11. Pull rear end of chain over and about 10” (260mm) past tail roller.
12. Use hoist to pull front end of chain over headshaft sprocket.
13. Move chain down boom until chain connector pin and lock key can be installed.
14. Install connector pin and lock key.
15. Tighten chain by pumping EPG into grease cylinder.
Time Augers
Ensure augers are balanced, as shown. If auger
timing is off, machine will bounce from side to
side even in normal digging conditions.
1. Remove bolts holding augers to auger shaft.
2. Rotate either auger as needed until augers
are balanced.
3. Install bolts.
4. Tighten.
Summary of Contents for RT70
Page 9: ...Overview 8 RT70 Operator s Manual About This Manual ...
Page 19: ...Safety 18 RT70 Operator s Manual Emergency Procedures ...
Page 31: ...Safety 30 RT70 Operator s Manual Attachment Safety Alerts ...
Page 83: ...Controls 82 RT70 Operator s Manual Seat ...
Page 89: ...Drive 88 RT70 Operator s Manual Shut Down ...
Page 97: ...Transport 96 RT70 Operator s Manual Haul ...
Page 103: ...Backhoe 102 RT70 Operator s Manual Finish Job ...
Page 123: ...Reel Carrier 122 RT70 Operator s Manual Finish Job ...
Page 129: ...Trench 128 RT70 Operator s Manual Finish Job ...
Page 141: ...Systems and Equipment 140 RT70 Operator s Manual Counterweights ...
Page 221: ...Specifications 220 RT70 Operator s Manual EU Declaration of Conformity ...