5.5.2.5 External Voltage Measurement Device
Required material (not include in scope of delivery):
•
Voltage measuring device
Figure 29: Cable routing to terminal strip (-X3)
Procedure:
1.
Locate
the terminal strip (-X3) (Figure 29).
2.
Open
the corresponding cable ducts.
3.
Route
the cables through the cable entry grommet.
4.
Connect
the cables to the terminal strip (-X3):
o
Phase
L1
on (-X3.11)
o
Phase
L2
on (-X3.12)
o
Phase
L3
on (-X3.13)
o
Neutral conductor
N
on (-X3.14)
5.
Close
the cable ducts.
6.
Fix
the cable with a cable clamp.