Original Operating Instructions
BATD0100-ES-1-480-1 (Outdoor)
Installation
O_BATD0100-ES-1-480-1_(Outdoor)_V2.2_US
Page
71
of
110
Depending on the demand the connection can be done in two ways.
Variant 1:
Buffered supply voltage via an UPS (optional)
Procedure:
1.
Locate
terminal strip (-X4) (Figure 24).
2.
Route
the cable through the cable entry grommet.
3.
Connect
PE, L and N and PE conductor of the
UPS
to the
terminal strip (-X4):
o
Protective conductor PE to (-X4.5)
o
Phase L to (-X4.1)
o
Neutral conductor N to (-X4.2)
4.
Connect
PE, L and N conductor of the
unbuffered
supply voltage
to
the terminal strip (-X4):
o
Protective conductor PE to (-X4.5)
o
Phase L to (-X4.3)
o
Neutral conductor N to (-X4.4)
5.
Fix
the cables with cable clamps.
Variant 2:
Unbuffered Supply Voltage
Procedure:
1.
Locate
terminal strip (-X4) (Figure 24).
2.
Route
the cable through the cable entry grommet.
3.
Bridge
the terminals as follows:
o
(-X4.1) to (-X4.3)
o
(-X4.2) to (-X4.4)
4.
Connect
PE, L and N conductor of the
unbuffered supply voltage
to
the terminal strip (-X4):
o
Protective conductor PE to (-X4.5)
o
Phase L to (-X4.3)
o
Neutral conductor N to (-X4.4)
5.
Fix
the cables with cable clamps.
Summary of Contents for BATD0100-ES-1-480-1