25
interface. Reserve a certain space for maintenance.The installing hole positions of manual
gas console SQK-A1 and SQK-B1 are same. See Figure 4-3.
Figure 4-3 Top view of gas console
9. HF box installation
(
“Part C in“Figure 4-2 system installation Figure”: HF Box
)
1) HF box should installed on the CNC torch moving body, close to the cutting torch,to
ensure that the length of the plasma gas pipe and protective gas pipe connected with the
plasma cutting torch is not more than 1.8m.
2) Reserve a certain space for maintenance. Check Figure 4-4 for the location of the
installing holes.
Summary of Contents for FLG-200HD
Page 9: ...5 Figure 2 1 System connection diagram ...
Page 43: ...39 Figure 5 2 SQK A1 front panel function Figure 5 3 SQK B1 front panel function ...
Page 74: ...70 4 System wiring diagram Figure 7 1 System wiring diagram ...
Page 77: ...73 2 Main circuit wiring diagram 2 Figure 7 4 FLG 200HD Main circuit wiring diagram 2 ...
Page 81: ...77 6 HF striking diagram Figure 7 8 HF striking diagram ...