NOTE: This step can be delayed until immediately prior to system commissioning if site
security cannot be guaranteed. If this option is required, isolate the service connections and
continue with the system installation procedure described in the following sections, including
checking the soundness of the system, flushing and cleaning, then return to this section later.
4.3 Fitting the Boiler
a)
Unpack the boiler and remove the outer casing by removing the two lower
fixing screws, pulling forward and lifting clear of the appliance. Place the
outer casing in a safe place until after installation (Figure 4/D), stand the
appliance in a vertical position.
4.2.2 Fitting the Flue Support Bracket
a)
Fix the flue support bracket to the wall using the screws provided as shown in
Figure 4/C.
4.2.3 Fitting the Connection Adapters
a)
Assuming that the service connections are to be completed using copper
pipework, fit the threaded connectors (supplied) to the pipe connections as
appropriate.
4 Installation Procedure
Figure 4/C: Fitting the Flue Support Bracket
24
Summary of Contents for VITODENS 200 WB2A
Page 8: ...2 6 Hydraulic Circuit Figure 2 B Hydraulic Circuit 2 Technical Specifications 8 ...
Page 23: ...Figure 4 B Full Wall template 4 Installation Procedure 23 ...
Page 76: ......
Page 77: ......
Page 78: ......
Page 79: ......