Connect the boiler
Depending on the design of the electrical system and the pipe system, connect the boiler to:
•
One phase with jumper
•
Two phases without jumper
•
Two phases with jumper
•
Three phases
One phase with jumper
MP4: 1.5 kW / 230 V~ / 6.5 A
MP6: 2.0 kW / 230 V~ / 8.7 A
Power cable:
3 x 1.5 mm
2
Fuse
protection:
10 A
Jumper:
N - X
Two phases without jumper
MP4: 2.25 kW / 400 V 2N~ / 5.6 A
MP6: 3.0 kW / 400 V 2N~ / 7.5 A
Power cable:
4 x 1.5 mm
2
Fuse
protection:
2 x 10 A
Two phases with jumper
MP4: 3.0 kW / 400 V 2N~ / 7.5 A
MP6: 4.0 kW / 400 V 2N~ / 10 A
Power cable:
4 x 1.5 mm
2
Fuse protection
MP4:
2 x 10 A
Fuse protection
MP6:
2 x 16 A
Jumper:
N - X
Two power steps MP4: 1.5/3 kW
MP6: 2/4 kW
Three phases
MP4: 4.5 kW / 400 V 3N~ / 6.5 A
MP6: 6.0 kW / 400 V 3N~ / 8.7 A
Power cable:
5 x 1.5 mm
2
Fuse
protection:
3 x 10 A
Two power
steps
MP4: 2.25/4.5 kW
MP6: 3/6 kW