Document Ref 942583-001 Rev 8
Page 5-3
Quantium 510 Installation Manual
Installation
• Side B of the dispenser is the opposite side. With the hydraulic door removed, side B has
the fuel inlet connections and access to the junction box.
5.3
Lifting
The responsibility for carrying out the procedures described in this manual lies with the
persons lifting and placing the dispenser.
The installer must supply all lifting equipment and ensure safe working practice at all
times.
The Quantium 510 Dispenser can be lifted by forklift truck under the wooden pallet or
through the metal C-Profiles.
5.4
Placement
Before placement on the island can take place, the following procedures must be carried
out:-
• Check that the electric cabling and piping arragements have been made in accordance
with the Installation drawing
• Check the pipes have been flushed before connecting the hydraulic components (if necessary,
contact the tank installer)
• Removal of stop plugs on fuel and vapour recovery pipes
• Preparation of mounting frame
Note : Ensure all mounting holes in the ground frame are free from debris
•
Fitting of seals for cable, fuel and vapour recovery pipe access
•
Sealing of non-used holes
IMPORTANT - Ensure Side A of the dispenser is positioned onto the island per
customer specifications. See Section 5.2 for locating Side A.
Lifting equipment can be
hazardous, and must be
rated to lift the weight of the
dispenser. Equipment
could fall and cause severe
injury or death. Stand clear
from the dispenser when
lifting and lowering.
Side B