5.
Putting into service
Prior to putting the machine into service first check whether the following
works have been carried out:
•
Safety, accessory and installation tools are removed from danger zone
•
Check mounting and aligning of machine, frame and rope departure
•
Check fastening of machine and frame
•
Screws are tightened and secured with pre-set torque (see table with
tightening torques in 9.1)
•
Brake shoe stroke and adjustment are checked
•
Brake test switches checked for correct adjustment and functioning
•
Brake test with one brake shoe each is carried out
•
Manual brake release checked for correct functioning
•
Rope guards are mounted *
1
), safety disconnection checked for correct
functioning if traction sheave cover is removed
•
Supply terminals, earthing of motor, forced ventilation, brake release
magnet connected, checked and secured
•
Special mountings (optional) 2. pulse generator checked for correct
functioning
•
Direction arrow (up/down) for the respective travel direction is clearly
visibly glued on expanding brake magnet above traction sheave
(label in motor terminal box in the as-delivered condition)
*
1
) In the case of older versions without rope guards one safety contact each
is provided below the drilled holes for the hydraulic jack. See chapter 8.2