4. Replacing Assemblies - Disassembly and Reassembly
To Remove A17 CBT Assembly
171
Operation Verification
1
Be sure the printer/terminal is on and that there will be a hard copy of the
information captured.
2
Connect power to the instrument, noting the time.
3
If the message “
Cs Oven is Up
” does not appear within 25 minutes,
there may be a problem with the connections to the A2 CBT Controller
assembly. Remove all power, disconnect the internal-standby battery,
and re-check your work.
4
When the message “
Operating Normally
” appears, the instrument is
operating. No further adjustments are needed.
Summary of Contents for 5071A
Page 2: ......
Page 40: ...1 Performance Tests Verifying Specifications 5071A Complete Performance Tests 24 ...
Page 48: ...2 Service Pre Troubleshooting Information 32 Figure 2 1 Instrument Top View ...
Page 168: ...3 Theory of Operation Functional Block Descriptions 152 Figure 3 5 Power Supply Block Diagram ...
Page 173: ......
Page 194: ...5 Replaceable Parts How To Order A Part 178 ...
Page 197: ......