Starting up
7 Starting up
This chapter details the procedure when first starting up.
7.1 Startup checklist
Authorised electricians
►
Check the following points before switching on the storage system:
✔
The ambient conditions are observed.
✔
All DC lines arefully and correctly connected.
✔
All Modbus cables are fully and correctly configured.
✔
The back-up fuse of the storage system is correctly configured.
✔
The electrical connecting cable satisfies all local and national directives for sizing
such cables.
✔
The electrical connecting cable is correctly fitted.
✔
A residual current operated device (RCD) is correctly installed (only necessary
in a TT network).
Page 64 of 115
KD-262 | Part-No 52199 | EN | Version 1.00
Summary of Contents for sonnenBatterie eco 7.0 Series
Page 7: ...Contents 17 Commissioning report 115 KD 262 Part No 52199 EN Version 1 00 Page 7 of 115...
Page 112: ...16 EU Declaration of Conformity Page 112 of 115 KD 262 Part No 52199 EN Version 1 00...
Page 113: ...EU Declaration of Conformity 16 KD 262 Part No 52199 EN Version 1 00 Page 113 of 115...
Page 114: ...sonnen GmbH Am Riedbach 1 D 87499 Wildpoldsried t 49 0 8304 92933 444 o info sonnenbatterie de...