5.2. Commissioning prerequisite
5.2.1.
Integration prerequisite
General
1.
Check the exact match of component product number and rating with your order.
2.
Battery energy storage system includes a user manual (system description, operating and safety instructions, maintenance
requirements, safe battery handling equirements/recommendations).
Integration check
1.
Battery and converter are installed in a perfectlly levelled ground concrete floor.
Please provide a photo of the concrete floor with a spirit level to validate that there is no inclination.
2.
The distance area around the system is at minimum as required by SOCOMEC (please find distance required below).
3.
Please provide a photo of the all installation (overviem - front side).
4.
Please provide a photo of the all installation (overviem - back side).
5.
"If Modem 4G option.
Check the well mounting of the antenna of the Modem in the roof of the C-Cabinet or other localisation.
Please provide a photo.
If it's in another localisation, please provide a plan."
6.
Verify the attachment of all unit to the concrete floor.
7.
Verify the attachment of all ucable gutter.
Sensors
1.
Presence of a Digiware sensor for current on the Load for CRD function.
2.
Make sure the sensor is accessible to the service team.
Installation Environement inspection and setting check
1.
The area around the system is accessible.
2.
The area is secured : no civil work, stable floor, etc.