7. POSITIONING
There are two types of installation possible: in line (side-to-side) and back-to-back. Concerning the back-to-back
installations, only the B-Cabs are back-to-back, there is free space behind the other cabinets. You must respect the correct
layout to ensure cable connections are sufficient.
You will find two examples of these installations below:
B-Cab
B-Cab
B-Cab
B-Cab
B-Cab
B-Cab
C-Cab
1
2
3
4
5
6
B-Cab
B-Cab
B-Cab
B-Cab
B-Cab
B-Cab
C-Cab
1
2
3
4
5
6
Figure 27. In line installation
Figure 28. Back-to-back installation
The C-Cab and B-cab anchoring holes in the floor of the concrete base must be pre-drilled using the template provided and
the mechanic anchoring installed before putting the cabinet in place.
Positioning of all cabinets is critical to ensure proper installation with the cable troughs from each battery cabinet.
Refer to the template provided to prepare the mounting location and install the cabinets into the designated place.
Drilling templates along with outline drawing dimensions will define the location of the cabinets. The drilling templates
provided are an overlapping modular set, you will need to attach the 4 parts of the template together before starting.
Follow the procedure described below to prepare the mounting location as detailed in the template.
7.1. Cabinets order
From top view, the cabinets always have to be positioned as follows: the C-CAB on the right side and the B-CAB on the left
side – from front face of the products. Installation must be started from the cabinet on the right (view below):
B-cab
B-cab
C-cab
Master
C-cab
Extension
Installation direction
Figure 29. Cabinets order