20
5.5. Switch grid connection
The AC power switch is an interface between the PV inverter and the public network.
The value of this switch (recommended 32 A,400V, 4 poles), must be designed by a qualified technician in
order to meet the local safety regulations.
Is also recommended the use of a differential switch type A / AC value of> 300mA.
Summary of Contents for SUNSYS - B10
Page 1: ...SUNSYS B10 Installation and Operation Manual ...
Page 15: ...15 D Check and ensure the device is properly fixed to the bracket in the proper direction ...
Page 36: ...36 ...
Page 37: ...37 ...
Page 38: ...38 ...
Page 39: ...39 ...
Page 40: ...40 ...
Page 41: ...41 ...
Page 42: ...42 ...
Page 54: ...54 ...