7. Initial start-up
7
- 61 -
951-171-021
Version 02
7. Initial start-up
Start-up check list
7.1 Inspections prior to initial start-up
YES
NO
Electrical connection carried out correctly
Mechanical connection carried out correctly
The performance data of the previously indicated connections correspond to the specifications stated in the Technical data
All components, such as lubrication lines and metering devices, have been correctly installed
Product protected with adequate pressure control valve
No visible damage, contamination and corrosion
Any dismantled protection and monitoring equipment has been reassembled and checked for correct function
All warning labels on the product are available and in proper condition
7.2 Inspections during initial start-up
No unusual noises, vibrations, accumulation of moisture, or odours present
No unwanted escape of lubricant (leakages) from connections
Lubricant is supplied free from bubbles
Bearings and friction points are provided with the planned amount of lubricant
In order to warrant safety and function, a person assigned by the operator must carry out the following inspections. Immediately eliminate
detected deficiencies. Deficiencies may be remedied by an authorized and qualified specialist only.
Summary of Contents for LINCOLN P203