6. Installation
6
- 59 -
951-171-021
Version 02
•
Lightly oil the reservoir inside and the
sealing lip of the follower plate
•
Slightly tilt the follower plate (6) in the
reservoir so that the side opposite of
the filler fitting (4) is at the highest
point.
•
At this point pass a cable tie (13) into
the area below the follower plate as
shown
•
Position the follower plate (6) horizon-
tally again. When doing so ensure that
the cable tie (13) creates an air gap.
•
Position the filling connection (14) of
the filler pump onto the filler fitting and
fill the space below the follower plate
with lubricant. Ensure that no air pock-
ets remain below the follower plate and
that no lubricant reaches the upper
side of the follower plate.
•
Remove the cable tie (13)
LINCOLN
LINCOLN
Priming of pumps with follower plate Fig. 17
6
13
14
Summary of Contents for LINCOLN P203
Page 84: ...EN 16 Annex 84 951 171 021 Version 02 16 China RoHS Table...
Page 85: ...Notes...
Page 86: ...Notes...
Page 87: ...Notes...