Priming of pumps with follower plate Fig. 16
6.8.4 Priming of pumps with follower
plate
In case of pumps without grease fill-
ing, before commissioning the space
below the follower plate must be
filled with grease. Any further fillings
take place only via the filler fitting (4)
or the optional filling connection on
the pump
CAUTION
Spring force
Slowly loosen the reservoir lid
holding it well. Wear safety goggles.
•
Unscrew the reservoir lid (1.1) anti-
clockwise from the reservoir
•
Carefully loosen (6.1) the spring from
the fixation at the follower plate (6)
•
Carefully pull the contact rod (6.2) out
of the follower plate (6)
•
Remove the reservoir lid together with
the spring and the contact rod
LINCOLN
1.1
1.1
6.2
6.1
6
Summary of Contents for LINCOLN P203
Page 84: ...EN 16 Annex 84 951 171 021 Version 02 16 China RoHS Table...
Page 85: ...Notes...
Page 86: ...Notes...
Page 87: ...Notes...