Operating the L1
007-4377-002
29
Powering On, Powering Off, and Resetting the Brick
Use a serial terminal cable connected to the console port on any one of the CR bricks.
From this perspective all functioning bricks with an L1 can be seen in the output of the
L1 config command.
001c07-L1>
config
:0 001c07 LOC
:1 001c11 U-F
:2 001c15 U-G
:3 001c33 U-H
:10 101i35 IIB
To power up/down/reset a non-router configuration from the L1, commands must be
targeted to all bricks:
001c05-L1> * power up
001c05-L1> * power down
001c05-L1> * reset
You can power on and power off a specific brick with the
power
command:
001c05-L1> power up
001c05-L1>
This will power on or power off only the locally attached brick. You can target other
specific bricks for the power on or power off commands by preceding the power
up/down command with a specific rack, and slot destination, such as:
001c05-L1> rack 1 slot 11 power up
001c05-L1>
or
001c05-L1> r 1 s 11 power up
001c05-L1>
This command requires from several seconds to several minutes to complete. Remember
that TP900 and D-brick2 options will always have to be manually powered on or off.
Summary of Contents for SGI Altix 3700 Bx2
Page 1: ...SGI Altix 3700 Bx2 User s Guide Document Number 007 4377 002 ...
Page 4: ......
Page 12: ......
Page 16: ......
Page 70: ...46 007 4377 002 3 System Overview Figure 3 1 SGI Altix 3700 Bx2 Series Systems ...
Page 85: ...Tall Rack 40U 007 4377 002 61 Figure 4 1 Tall 40U Rack ...
Page 88: ......
Page 90: ...66 007 4377 002 5 CR brick Figure 5 1 Front and Side View of CR brick ...
Page 128: ......
Page 136: ......
Page 144: ......
Page 184: ......