Commissioning
Detailed commissioning steps
10
103 | 118
Building Technologies
A6V10211100_f_en_--
Fire Safety
2015-12-15
10.8.15 Remove the elements
If you have uninstalled an C-NET device for good, the corresponding elements,
e.g. the 'Cerberus-Engineering-Tool' must be removed from the logical structure
trees in Zone. You can search for elements using the 'Find' function.
You will find more information in document A6V10210424. See chapter 'Applicable
documents'.
10.8.16 Testing detectors
The commissioning personnel perform the function test for the ↑ automatic fire
detectors and the 'Manual call points'.
You will find additional information about the individual steps on the specified
pages.
ϖ
The ↑ detector line has been commissioned.
1. Switch the test mode on. Link [➙ 104]
2. Initiate the detector. Link [➙ 103]
3. Switch normal operation on. Link [➙ 104]
4. Test the logged test activations. Link [➙ 103]
10.8.16.1 Activate the detector
ϖ
DETECTOR TEST is switched on.
1. Activate all automatic 'Detectors' and 'Manual call points' using the
corresponding tools.
2. Write down the sequence of the test activations.
The ↑ alarm indicator for the activated detector flashes at each test activation.
If an ↑ external alarm indicator is connected and correspondingly configured,
the external alarm indicator also lights up.
You will find information about triggering detectors in document A6V10212047.
See chapter 'Applicable documents'.
10.8.16.2 Testing logged test activations
1. Test the logged test activations. This can be done in two ways:
– ↑ Person Machine Interface: Select 'Event memory' in the main menu.
– Cerberus-Engineering-Tool: Select the 'Commissioning' > 'Upload site
event memory' menu items.
2. Rectify existing errors if necessary, e.g., if the ↑ alarm indicator has not flashed
or no test entries exist.