The inversion mode timing chart shows the operation of
each electrical component in the inverter section of the
finisher when 2 A4 copies are made in continuous
operation.
*1
The finisher ON signal is generated from the copier
when the copier main motor starts turning after the Start
key is pressed. The stopper drive motor starts moving
the inverter stopper plate to the position specified by
each paper size.
*2
Just before the paper enters the inverter tray, the speed
of the inverter transport motor is reduced. (The speed
change timing varies according to paper size.) This is to
have the leading edge of the paper hit against the paper
stoppers gently.
*3
Just when the paper leading edge hits the paper
stoppers, the stopper drive motor starts turning to move
the paper upward. Then soon the motor turns in the
opposite direction to return the inverter stopper plate to
the position specified by the paper size.
When the finisher ON signal turns off, the stopper drive
motor turns to return the inverter stopper plate to its
home position.
To Finisher
Copier
Inverter
[A]
[B]
[C]
[D]
[E]
[F]
[G]
[E]: Inverter Guide Roller (In)
[F]: Inverter 3rd Sensor
[G]: Inverter Guide Roller (Out)
[A]: Copier Exit Rollers
[B]: Inverter Entrance Sensor
[C]: Inverter Entrance Rollers
[D]: Inverter 2nd Sensor
1 July 1994
Finisher
2-153
Summary of Contents for PCU10
Page 3: ...SECTION 1 OVERALL MACHINE INFORMATION...
Page 36: ...SECTION 2 SECTIONAL DESCRIPTIONS...
Page 46: ...2 1 11 Paper feed operation Circuit diagram Paper Feed 1 July 1994 2 10...
Page 59: ...2 2 7 Optics operation Circuit diagram 1 July 1994 Optics 2 23...
Page 69: ...2 3 9 OPC unit operation Circuit diagram 1 July 1994 OPC Unit 2 33...
Page 76: ...2 4 5 Charging operation Circuit diagram OPC Charge 1 July 1994 2 40...
Page 82: ...2 5 4 Eraser operation Circuit diagram Erase 1 July 1994 2 46...
Page 94: ...2 7 7 Cleaning unit operation Circuit diagram Cleaning 1 July 1994 2 58...
Page 100: ...2 8 7 Timing chart OPC Filming Removal 1 July 1994 2 64...
Page 106: ...2 9 11 Development operation Circuit diagram Development 1 July 1994 2 70...
Page 121: ...2 11 3 Process control flow 1 July 1994 Process Control 2 85...
Page 138: ...2 13 9 Duplex exit operation Circuit diagram Duplex and Paper Exit 1 July 1994 2 102...
Page 156: ...ADF 1 July 1994 2 120...
Page 161: ...Exit sensor 1 July 1994 ADF 2 125...
Page 162: ...2 14 10 ADF operation Circuit diagram ADF 1 July 1994 2 126...
Page 178: ...2 16 9 LCT operation Circuit diagram Large Capacity Tray 1 July 1994 2 142...