![Raven Sidekick Pro ISO Installation & Operation Manual Download Page 47](http://html.mh-extra.com/html/raven/sidekick-pro-iso/sidekick-pro-iso_installation-and-operation-manual_789032047.webp)
CHAPTER
5
P/N 016-0171-509 Rev. E
43
CHAPTER 5
OPERATION
SIDEKICK PRO™ ISO PRIMING AND CALIBRATION
Before starting application of injected products, perform the following procedures to ensure the system is properly
calibrated and ready for chemical application:
1. Verify control console setup
2. Prime the injection pump
3. Calibrate the injection pump
VERIFY CONTROL CONSOLE SETTINGS
Review the Virtual Terminal Calibration section on page 32 and verify that the correct settings for the chemical
injection product are programmed for the correct product node or product number.
PRIME THE INJECTION PUMP
1. Open the hand valve(s) between the supply tank and injection pump.
2. Set the hand valve on the injection pump outlet to recirculate product back to the supply tank.
3. Lift the plunger handle on the pump calibrator to the top of the calibration cylinder.
4. Verify the following conditions are present:
a. Vacuum pressure for the injected product must be less than 5.5 PSI [37.92 kPa]
b. Injection pump discharge pressure must be less than 12 PSI [82.7 kPa]
c. Injection product pump mode must be set to “CAL/PRM” (Calibration/Prime)
d. Injection pump product master switch must be set to on
5. On the UT display, set the pump mode on the main product control screen to “CAL/PRI/RNS.”
Tools
Summary of Contents for Sidekick Pro ISO
Page 8: ...CHAPTER 1 4 Sidekick Pro ISO Installation Operation Manual ...
Page 16: ...CHAPTER 2 12 Sidekick Pro ISO Installation Operation Manual ...
Page 46: ...CHAPTER 4 42 Sidekick Pro ISO Installation Operation Manual ...
Page 70: ...CHAPTER 7 66 Sidekick Pro ISO Installation Operation Manual ...
Page 80: ...Index 76 Sidekick Pro ISO Installation Operation Manual ...