4.0 WEATHER STATION CONCRETE BASE:
SUPPLIED COMPONENTS
(3) ½” x 12” long “L” Anchor
Bolts
(9) ½” Nuts
(3) Flat Steel Washers
(1) Stainless Steel Template
(1)
1 ½” Dia. Long Sweep
Elbow
INSTALLER SUPPLIED
(1)
2” x 4” x 10’-0” piece of
forming lumber
(4) 16p Double Headed nails
10’-0 “ length of form wire
½ yard of concrete
Duct Tape
TOOLS REQUIRED
Claw Hammer
Hand Saw
Saw Horse
Shovel
Pliers & Wire Cutters
INSTALLATION:
For the following procedures - Refer to
FIGURE 4
below.
1.0
The Tower for the “PRO”
Weather Station - attaches to a user
supplied poured concrete
foundation - constructed as shown
in
FIGURE 4
below.
2.0
Dig the required foundation
hole - with a 24” square top
and slanting outward sides, to the
bottom of 32” square. The
“Sloping” sides of the foundation are
very
IMPORTANT
in providing the
necessary support to the weather
station tower, in preventing it from
“leaning” or falling over, due to
wind load on the station.
3.0
Determine the proper location of the
long sweep elbow and dig a small
cavity to accept the end of the elbow
that will protrude beyond the
concrete base.
4.0
Construct the concrete form
with 2” x 4” lumber and 16p
double-headed nails.
Center the form over the dug
hole. Adjacent to the long
legs of the form that extend
beyond the hole, drive four
stakes into the soil. Level
the form. Secure the form
to the stakes with 8p nails -
making sure that the form
remains “level”.
5.0
Place a piece of duct tape
over one end of the 1 ½”
diameter long sweep elbow.
Insert the elbow into the
hole, with the taped end
into the small cavity that
you have dug on one side of
the hole.
Summary of Contents for WS-PRO
Page 2: ......
Page 10: ...Page viii...
Page 16: ...Page 6 FIGURE 2 MAGNETIC DECLINATION FOR THE CONTIGUOUS UNITED STATE...
Page 21: ...Page 11 FIGURE 4 CONCRETE BASE DETAIL FIGURE 5 ANCHOR BOLT TEMPLATE DETAIL...
Page 24: ...Page 14 FIGURE 6 EXTERNAL WIRING DETAIL AT THE PRO SH WEATHER STATION...
Page 27: ...Page 17 FIGURE 7 EXTERNAL WIRING DETAIL AT THE PRO PH WEATHER STATION...
Page 33: ...Page 23 FIGURE 10 SOLAR PANEL INSTALLATION DETAIL...
Page 35: ...Page 25 FIGURE 11 CROSS ARM MOUNTING INSTALLATION OF 034A WIND SENSOR...
Page 48: ...Page 38 FIGURE 21 INSTALLATION AT CENTRAL COMPUTER FOR DIRECT CONNECTED WEATHER STATION...
Page 50: ...Page 40 FIGURE 22 INSTALLATION AT CENTRAL COMPUTER FOR TELEPHONE CONNECTED WEATHER STATION...
Page 73: ...Page 63 FIGURE 28 TYPICAL 3 ROD GROUNDING GRID DETAIL...
Page 75: ...Page 65 FIGURE 30 TESTING OF SOLAR RADIATION SENSOR...
Page 76: ...Page 66 FIGURE 31 TESTING OF RAIN GAGE...
Page 77: ...Page 67 FIGURE 32 TESTING OF TEMPERATURE RELATIVE HUMIDITY SENSOR...
Page 78: ...Page 68 FIGURE 33 TESTING OF AIR TEMPERATURE PROBE...