Preventive Maintenance | Visual Inspection
63
Cooling Pad | Installation and Operation Guide Rev B | Doc P/N: 080205039E
5.3 Visual Inspection
As part of the visual inspection, verify the following:
z
All holes between the housing walls and the cooling pad system
are sealed
z
Cooling pads are not damaged or clogged
z
Maintenance valve (A) is open
z
Bypass valve (B) is adjusted as done during
z
Drainage valves (11) on both side of the cooling pad system are
closed
z
Plug (25) at the end of the reservoir channel is closed
z
Valve (61) on the bottom of the reservoir channel is closed
25
61
11
A
B