Oracle Field Service
Using Core Application
Chapter 2
Dispatcher Activities
that contains other segments of the same segmentable activity, such other segments will also be protected against
automatic recalculations.
1.
Select the segment started in an activity and click the Adjust Time link.
The Duration and Time to Complete fields appear.
2.
Adjust the Time to complete value under these conditions:
Option
Description
Start a segment
If the route contains pending segments of the same segmentable activity, they are
not adjusted automatically with the time adjusted to the started segment. This action
causes recalculation of the activity segments in the routes of next days. The routes may
be adjusted so that the total duration of the segmentable activity is preserved. If all
remaining segments of the segmentable activity are located in today's route, and the
started segment adjustment causes their total duration to exceed the total duration of
the activity, you must increase the duration of the activity accordingly.
Cancel a segment
If you cancel one of the segments of a segmentable activity, no other segment in the
same route is affected. You can change the total duration of the segmentable activity
(the Time to complete), though.
Mark the segment as cancel/not
done
You can adjust the duration of a specific canceled /not done segment. The duration
adjusted for a segment does not modify the duration of other segments.
Reorder segment within a route
You can adjust the duration of the reordered segment. No other activities and/or
segments in the same route are affected.
External events
These external events cause recalculation of all segments of the existing activities of
such type:
◦
Adding an activity to the route
◦
Canceling an activity in the route
◦
Starting and completing an activity before the segmentable activity segment in the
route
◦
Changing the time slot, duration, or other parameters affecting the ETA
◦
Calendar changes such as working and non-working hours, shifts, and so on
The duration is adjusted according to the new settings and, consequently, may change
the total number of segments. However, any changes made to the segments manually
are preserved even if the activity type parameters change.
The segment duration is adjusted. If you change the basic parameters of the activity type such as the Minimal
duration of a single segment and Maximal total duration of segments created for a particular day, the
segments of the existing activities of such type are recalculated. The duration of such activities is adjusted
according to the new settings, and this in turn may change the total number of segments. However, any
changes made to the segments manually are preserved even if the activity type parameters change.
Teamwork
Teamwork is a feature that allows a resource or group of resources to assist each other to complete work.
110
Summary of Contents for 21C
Page 1: ...Oracle Field Service Using Core Application 21C ...
Page 4: ...Oracle Field Service Using Core Application Inventory 245 Resources 252 End Your Day 263 ...
Page 6: ...Oracle Field Service Using Core Application Preface ii ...
Page 18: ...Oracle Field Service Using Core Application Chapter 2 Dispatcher Activities 12 ...
Page 73: ...Oracle Field Service Using Core Application Chapter 2 Dispatcher Activities 67 ...
Page 75: ...Oracle Field Service Using Core Application Chapter 2 Dispatcher Activities 69 ...
Page 187: ...Oracle Field Service Using Core Application Chapter 3 Field Resource Activities 181 ...
Page 204: ...Oracle Field Service Using Core Application Chapter 3 Field Resource Activities 198 ...
Page 274: ...Oracle Field Service Using Core Application Revision History 268 ...