Installation
31
-
Figure 15: cables access
inside the shutterbox
To dismantle the cables on the shutter box, loosen the four screws on the
shutter box housing (it is not necessary to loosen the screws completely).
Remove the cover of the shutter housing by tilting it backwards and pulling
upwards. Now the end of the cable (
shutter box. Now loosen the screw for the strain relief under the cover and pull
out the slide (
in blue). Now you can unscrew the shutter cable and,
after laying the cable, reassemble it in the reverse order.
Now that the three main components have been successfully assembled, two
connections must be connected. The first connection is the Ethernet cable to a
computer or switch. The second connection is the power supply. The entire
system is supplied with 24 V. The power supply unit is included in the delivery.
If your machine has a power supply of 24 V DC with a current of at least 3A,
the entire system can be supplied by the machine and the power pack can be
omitted.
Summary of Contents for Bottom-Up GIS 450i G7
Page 1: ...Operators Manual Bottom Up GIS 640i G7 and 450i G7 Glass Inspection System ...
Page 11: ... Technical Data 11 Figure 1 Dimensions mm shutter system ...
Page 12: ... 12 Figure 2 Dimensions mm control cabinet ...
Page 13: ... Technical Data 13 Figure 3 Dimensions mm CTL 4M ...
Page 20: ... 20 CTL 4M FF optics Figure 5 spot size diagram ...
Page 27: ... Installation 27 Figure 10 camera distance ...
Page 44: ... 44 Figure 27 Linescan in PIX Connect software customized Layout ...
Page 52: ... 52 Appendix A Control cabinet Figure 34 Wiring diagram of control cabinet ...
Page 57: ...Bottom Up GIS MA E2022 04 A ...