Mounting of FH-L Series
• Make sure to tighten all screws in mounting.
• For good ventilation, provide a clearance of 50 [mm] or more above the Sensor Controller away
from other devices in the normal floor mounting. For the right and left sides, provide a clearance of
30 [mm] or more, and for the back side, 15 [mm] or more. These clearances are also required when
mounting multiple Sensor Controllers side by side. For the back mounting, the back-side clearance
of 15 [mm] is not required.
• Do not install the product immediately above significant heat sources, such as heaters, transform-
ers, or large-capacity resistors.
• Do not install the Sensor Controller in a cabinet with high-voltage equipment installed.
• Mount the Sensor Controller at 200 [mm] or more from power cables apart.
l
Mounting the base of the Sensor Controller (Floor mounting)
Clearance: 50 mm
Clearance: 30 mm
Clearance: 15 mm
Clearance: 30 mm
52.9
15
59
Four, M4 depth 6.5
10.5
80
22
100
• Recommended tightening torque: 0.54 to 0.6 N•m
• The tolerance: ±0.2 mm
5 Setup and Wiring
5-14
FH Series Vision System Hardware Setup Manual (Z366-E1)
Summary of Contents for FH-2 Series
Page 8: ...Manual Structure 6 FH Series Vision System Hardware Setup Manual Z366 E1...
Page 34: ...Revision History 32 FH Series Vision System Hardware Setup Manual Z366 E1...
Page 48: ...1 Confirm the Package 1 14 FH Series Vision System Hardware Setup Manual Z366 E1...
Page 58: ...2 Overview of FH series 2 10 FH Series Vision System Hardware Setup Manual Z366 E1...
Page 148: ...3 Configuration 3 90 FH Series Vision System Hardware Setup Manual Z366 E1...
Page 235: ...I Index I 1 FH Series Vision System Hardware Setup Manual Z366 E1 I...
Page 242: ...Index I 8 FH Series Vision System Hardware Setup Manual Z366 E1...
Page 243: ......