3. Check and Preparation
3-27
D6FZ-FGT
The following shows the supply pipe specifications.
Applicable diameter: D6FZ-FGT200 / 8A(Rc1/4) D6FZ-FGT500 / 15A(Rc1/2)
Precautions for piping
When piping, fix with the part of conduit by wrench.
And secure piping with the tightening torque of the following list.
Model
Tightening torque
D6FZ-FGT200
12 to 14N.m
D6FZ-FGT500
31 to 33N.m
・
Fix with only the conduit part when piping. Do not fix with other parts, or the product
might be damaged.
・
When fixing with the part of flow channel by wrench, cover the body with something
like a waste cloth. If holding the body with a wrench directly, the body might be
damaged.
・
Check the flow direction before mounting pipes.
・
Do not apply force on other than conduit.
・
Make sure that foreign objects do not enter inside the body when piping.
・
Be sure to mount the body horizontally, otherwise the detection accuracy might be
worse.
・
Don't mount the body facing the control panel downward. Otherwise, the mist and
dust in the pipe accumulates and it might cause breakdown.
Flow Direction