4.2. Stack Switchgear Electrical Connections
Before making any connections, ensure that the service disconnect in
is in
the
OFF
position.
The Stack Switchgear is configured for a specific battery topology based on the
details provided to Nuvation Energy during order fulfillment. Failure to use the same
number of Cell Interface modules and/or using a different battery topology will result
in undesirable Stack Switchgear behavior.
+ Please contact
if there is a change in the system
design that would require a Stack Switchgear configuration update.
4.2.1. Getting Started
▪
Step 1: Ensure system is de-energized
▪
Step 2: Ground the Stack Switchgear
▪
▪
▪
▪
Step 6: Connect to external PC
▪
Step 7: Connect Cell Interface Link bus
▪
Step 8: Connect Battery Stack and DC Bus
Below is a overview image of the external interfaces available on the front of the Stack Switchgear.
Figure 11. Stack Switchgear external interfaces