Installing the Cabinet
DS1000 Hardware Manual
Section 1: Installation Basics
◆
1-5
1
Installing the Cabinet
Planning the Installation
Before installing the common equipment, you should mount a Main Distribution Frame (MDF) plywood
backboard in a centrally located spot. A 1/2 sheet of plywood (4’ x 4’) should be more than adequate (see
Figure 1-1
Installation Layout
below). Mount this backboard using suitable fasteners, taking care to adhere
to standard installation practices and local codes.
The equipment cabinet requires a three-prong, dedicated 110 VAC 60 Hz circuit (NEMA 5-15 receptacle)
located within 4 1/2’ feet of the cabinet’s lower left corner.
Normally, you install the extension blocks and trunk/AUX jacks to the right of the Main Cabinet.
!! Important !!
•
Local codes may prohibit you from installing extensions, trunks and optional equipment in
the same blocks.
•
Do not plug in the 25-pair extension cable with power applied.
Figure 1-1: Installation Layout
80200 - 37
Plywood backboard
Trunk/AUX
RJ-25C Jacks
4'
4'
Station
Blocks
Dedicated
AC Outlet
Surge
Protector
To telco
ground
Summary of Contents for DS1000
Page 6: ...Table of Contents iv Table of Contents DS1000 Hardware Manual...
Page 20: ...The Extension Block 2 4 Section 2 Trunk and Extension Cabling DS1000 Hardware Manual...
Page 42: ...Keyset Self Test 4 18 Section 4 Optional Equipment DS1000 Hardware Manual...
Page 58: ...Parts List 6 8 Section 6 Specifications and Parts DS1000 Hardware Manual...