GTR 8000 Base Radio
Table 3-1
Activities for Site Preparation
Activity
Description of Activity
Chapter Reference
Review the site plan.
•
Prevents potential on-site and
off-site interference by local
trunked systems.
•
Minimizes cable lengths.
•
Determines the location of
telecom equipment.
•
Chapter 4 "Site Design and
Development"
Determine site access and
security.
Outlines of site access and security
measures.
• Chapter 3 "Site Acquisition"
•
Chapter 4 "Site Design and
Development"
Review safety
considerations.
Outlines general, installation, and
environmental safety guidelines and
requirements as well as OSHA related
considerations.
• Chapters 2 "Safety Summary"
• Chapter 5 "Communications Site
Building Design and Installation"
Schedule installation of
telephone service.
Ensures options and functions of on-site,
two-way communications for personnel
safety and maintenance.
• Chapter 3 "Site Acquisition"
Review grounding
specifications.
Ensures the site meets or exceeds the
Quality Audit Checklist in Appendix
F as well as the Power and Grounding
Checklist in Appendix D.
• Chapter 6 "External Grounding"
• Chapter 7 "Internal Ground"
• Chapter 8 "Power Sources"
•
Chapter 9 "Transient Voltage
Surge Suppression"
Schedule installation of
site power.
Covers grounding, power sources, and
surge protection.
• Chapters 6 "External Grounding"
• Chapter 7 "Internal Ground"
•
Chapter 8 "Power Sources"
•
Chapter 9 "Transient Voltage
Surge Suppression"
3.3.2 General Equipment Inspection and Inventory
Recommendations
Motorola recommends that an inventory of all equipment is taken with a Motorola representative to ensure that the
order is complete. Carefully inspect all equipment and accessories to verify they are in good condition. Promptly
report any damaged or missing items to a Motorola representative.
Do not tamper with factory configuration settings for these devices. This includes software
configuration, firmware release, password, and physical connections. Motorola has configured and
connected these devices to meet specific performance requirements. Tampering with these devices
may result in unpredictable system performance or catastrophic failure.
3-8
6871022P86-A - November 2012
Summary of Contents for GTR 8000
Page 2: ......
Page 4: ......
Page 6: ......
Page 14: ......
Page 18: ......
Page 22: ......
Page 26: ......
Page 60: ......
Page 177: ...5 8 1 3 VHF Tuning Procedure Figure 5 1 Preselector Tuning VHF 6871022P86 A November 2012 5 7 ...
Page 181: ...5 8 2 3 UHF Tuning Procedure Figure 5 2 Preselect Tuning UHF 6871022P86 A November 2012 5 11 ...
Page 230: ......
Page 234: ......
Page 244: ......
Page 286: ......
Page 300: ......
Page 338: ......