72
35-127 M
Description Of Machine and Controls
ATB Components
CABLE REEL
The ATB cable is wound onto a spring loaded cable reel which is bolted to the left side of the boom base�
The reel allows the cable to pay-out and pay-in as the length of the boom is changed� The cable reel has
slip rings which allow electric current to flow even while the reel is turning� This cable and reel assembly
is also used to measure boom extension when the Boom Truck is fitted with an RCI system�
SHEAVE ASSEMBLIES
The sheave assemblies are installed on the side of the boom and, if equipped, on the side of the jib� The
sheaves should be checked periodically to make sure they are free turning and smooth� Rough or
sticking sheaves should be replaced as they could damage the ATB cable�
LIMIT SWITCH
An ATB switch is mounted on the left side of the boom tip� The switch is normally open� During operation
the switch is held closed by a counterweight suspended from the switch lever by a chain� The closed
limit switch allows current to close the relay in the junction box in the pedestal� When the load block (or
downhaul weight) is lifted too high, it will lift the counterweight� This action will cause the limit switch to
open, breaking the circuit to the relay� This, in turn, de-energizes the coil on the unloader block assembly�
ATB Components
1 2-Block Wire
5 2-Block Chain
2 2-Block Reel
6 2-Block Weight
3 Sheave Assembly
7 2-Block Wire Going to Electrical Box
4 2-Block Switch
Summary of Contents for 35-127 M
Page 1: ...OPERATORS MANUAL LOAD KING 35 127 M C1046093 REV A FEBRUARY 09 2022...
Page 2: ...PAGE INTENTIONALLY LEFT BLANK...
Page 48: ...PAGE INTENTIONALLY LEFT BLANK...
Page 63: ...63 Description Of Machine and Controls Operator Controls 5 3 2 4 8 7 1 9 10 6...
Page 79: ...79 REPAIRS ADJUSTMENTS REMARKS ITEM REQUIREMENT DATE...
Page 96: ...PAGE INTENTIONALLY LEFT BLANK...
Page 124: ...PAGE INTENTIONALLY LEFT BLANK...
Page 131: ...131 35 127 M Master Lube Chart 1 2 5 11 12 3 4 6 8 9 7...
Page 132: ...132 35 127 M Maintenance...
Page 150: ...150 35 127 M Maintenance...
Page 172: ...PAGE INTENTIONALLY BLANK...
Page 176: ...PAGE INTENTIONALLY LEFT BLANK...
Page 201: ...201 Repairs Adjustments Remarks Log ITEM REQUIREMENT DATE...
Page 202: ...PAGE INTENTIONALLY LEFT BLANK...
Page 209: ...209 Torque Specs SAE Metric...
Page 210: ...210 35 127 M Appendix...
Page 212: ...PAGE INTENTIONALLY LEFT BLANK...
Page 213: ...Notes...
Page 216: ...35 127 M Operator Manual...