80
Operating Manual
OMBG3000 – Iss.01
© Copyright 2016
4.16
Final Checks
Ensure all gas connections to the system are leak free – refer to section
of this operating manual for instructions on how to
perform this.
Ensure the gas inlet and gas outlet ball valves are open (refer to
annotation 12 on
Figure 2 - BIOGAS 3000 internal
components) these must be in the
vertical position.
Ensure the drain ball valve, if fitted, is closed (see annotation 9 on
Figure 2 - BIOGAS 3000 internal
components), this must be in the
horizontal position.
Ensure the calibration ball valve is closed (see annotation 10 on
Figure 2 - BIOGAS 3000 internal
components), this must be in the
vertical position.
Turn the power on to the system. Within one minute of power being
applied, the module will turn on and display the BIOGAS 3000 logo,
shortly followed by the ‘system self-test’ screen (see
The first time the module is started after the self-test has successfully
completed, the ‘first time run set-up wizard’ will begin – please refer to
section
in this manual for details of this process.
It is strongly recommended that a known concentration of gas be
passed through the system to ensure that it still reading correctly
following installation. Refer to the
this operating manual for further information on this process.
Note: For further information please contact our technical support team at
(800) 968-2026 or email